Current Projects

Construction Projects Around the City banner

Current Projects

 Following is  information on current construction projects around the city, including  city projects as well as private construction projects.  Storm Water Pollution Prevention Plan (SWPPP):  any construction site / land disturbance over an acre of property is required to have a SWPPP in place and will be monitored by the city's storm water manager for compliance.  For questions or concerns please contact, Daniel Schuler - Clearfield City Public Works Inspector/Storm Water Manager/Fleet Superintendent at 801-525-4404 (office), 801-940-2078 (cell), or email.  

Last updated: May 11th, 2017 

                             Project   / Contractor Address / Location

Under Construction artwork
Park Village, 
Ivory Homes.  (SWPPP) / 1000 West 300 North
Status:  2 lots remaining; Six lots are currently under construction,
subdivision is near completion .

Under Construction artwork
University Ridge Subdivision, 
Mark Koehler. (SWPPP) / 2000 East 926 South
Status: Building town homes.  Asphalt installed Contractor will continue
 to install  driveways and repair some sections of curb that are damaged,
                             also work on areas that need landscaping, installing sod througout the project.  
                              Construction on commercial  building located north corner of 2000 East 926 South
                             intersection, will be asphalting parking lot within next two weeks.                             
Under construction artwork 
Z Street water line project, Kapp Construction/Freeport Center.
Status: Started installing water line on 4-14-17.  water line replacement is to
schedule.  5-11-17 start water line testing for new water line installed. 
  
under construction artwork
West Square, Ironwood. (SWPPP)     / 700 South, S.R. 193 & Depot St.
Status:  All utilities are installed to city standards. Contractor started installing
power for Apt. 
under construction artwork
Security Title,  
1795 East Legend Hills Drive.
Status: All utilities are installed to plan. 5-10-17 contractor installed footings for fondation. 
under construction artwork
 Let Them Be Kids,  
Elk Valley Const. (SWPPP) / 1600 South 823 West
 Status:  New daycare building is under Construction, will asphalt parking
 lot the next  week.  
under construction artwork
City Centre Apartments, 
Highmark Const.  (SWPPP) /50 South State St.
Status:  Cleaning up site, hauling away dirt;  installing footings
  and foundations for underground parking area, continuing construction on the
                              apartments,  started construction on the third level of the apartments this week
                             and installing windows and doors.   
under construction artwork
Jon's Park, 
Wall Bros. Const.  (SWPPP) / Pacific Street, 125-160 North
Status: Completed walk through; contractor has punch list to go through and fix listed items, sidewalk, curb n gutters, and landscaping.
under construction artwork
USTAR INNOVATION CENTER, 
Sparrow Hawk LLC Falcon Hill/MIDA (SWPPP).
Status: Installed all the utilities on site, water,sewer, and storm drain. installed
 footings and foundation. next week the building will start going up.
construction
Clearfield Station, Thackeray Garn,  (SWPPP)  State st. & 1000 East.  
Status:  Relocate existing utilities, put up construction fence, grading site and
 setup SWPPP.            
construction
Wilcox Farms Phase 5,
Josh Staheli Excavating/ 823, 848 West 1600 South
Status:
 project near completion, contractor will work on cleanup, install lighting,
 and landscaping in the park strip.                                    
  construction site sign   
Americold addition, Americold (SWPPP)/ 1755 East 1700 South
Status: Construction on new road along west end of project and footings and
 foundation for new building, installing the utilities.  
construction sign
650 North I-15 Interchange/Intersection Improvement Project,
UDOT (SWPPP) / 650 North & I-15 Interchange. 
Status: Construction on 650 North, under the overpass (I-15) installing
                             storm drains, relocate fire hydrant on 650 N.
                             For questions or concerns please contact Bill Crowley,
                             Project Manager for COP construction  (801-597-4839). 
                          
                           
construction artwork

Contact Info

Public Works

497 South Main
Clearfield, UT 84015
801-525-4404
Hours: 8 a.m.-5 p.m.