 The following is  information on current construction projects around the city. This is not a comprehensive list. 

300 N Roadway Improvements

Construction Begins: February 11, 2020
Estimated Completion Date: July 6, 2020

This project is headed up by West Point City with Clearfield City assisting with some of the cost. The project scope will encompass storm water, water, curb and gutter, streets and lighting improvements from 1000 W to 1500 N.

300 N from 1000 W to 2000 W will be closing April 22-24 to mill the road. The road then will be reduced to neighborhood one way traffic until the end of June. 

Impacts: Traffic, Pedestrian Access, Storm Water, Water Pressure, Road Closures

 



View: Maps, Project Timeline, 300 N Closure Map

Texting Service Available

Text alerts are available for this project text the following code to 801.525.2701 to start receiving updates.

"300N"

University Park Boulevard Closure

Construction Begins: February 29, 2020
Estimated Completion Date: March 8, 2020

Davis Weber Canal Company is currently are installing a box culvert to deliver their water services. They will be closing University Park Boulevard to continue their efforts along the canal. The road will remain closed throughout this whole time frame.
This project is completed.

Impacts: Traffic, Pedestrian Access, Trail Closure, Road Closures

 



View: Maps

Texting Service Available

Text alerts are available for this project text the following code to 801.525.2701 to start receiving updates.

"LegendHills"

 

800 North Roadway Improvements

Construction Begins: March 23, 2020
Estimated Completion Date: November, 2020

Construction work between 450 West and 50 West on 800 North to replace curb and gutter, asphalt, secondary water lines, and culinary waterlines. At some point, the main waterline will need to be shut down in order to make a few connections, however, customers will be notified 2 business days in advance. 
Pre-construction meeting held March 12th with Staker Parson and Sunset City. Work began on March 20th on demolition of curb and gutter on Sunset side of project and replacement of secondary waterline. One lane of roadway is open to local traffic only. 

Impacts: Traffic, Pedestrian Access, Road Closures, Water Shut Down

 



View: Maps

Texting Service Available

Text alerts are available for this project text the following code to 801.525.2701 to start receiving updates.

"800N"

 


Legend Hills Phase 3 Water and Storm

Construction Begins: April 20, 2020
Estimated Completion Date: June, 2020

Construction work will occur near 1850 East 1400 South to install a new waterline and storm drain line for future developments in the area of Legend Hills, just south of Hwy 193. The project will occur in two phases, the first phase will install the waterline and first section of storm drain line, and the second phase will install the remaining storm drain line. At some point, the main waterline will need to be shut down in order to make a few connections, however, customers will be notified 2 business days in advance. 
Pre-construction meeting held March 25th with Great Basin Development. 

Impacts: Water Shut Down

 



View: Maps

Texting Service Available

Text alerts are available for this project text the following code to 801.525.2701 to start receiving updates.